Types of Construction Delay Basic Distinctions:
•Excusable & Non-Excusable
•Compensable & Non-Compensable
•Concurrent & Non-Concurrent
•Critical vs. Non-Critical

hashtagExcusable Delays:

“Excusable delays are caused by conditions that are reasonably unforseeable and not within the contractor’s control”

Non-Excusable Delays:
•Late hashtagperformance of subcontractors • Late performance by suppliers
•Faulty workmanship by the contractor or subcontractors
•A project specific labor strike caused by either the contractor’s unwillingness to negotiate or by unfair job practices

– Delay Analysis methodologies

1》As Planned versus As Built Comparison
• Simple to Prepare
Shortcomings
•No information on particular delay events
•Similar to “Total Cost” approach

2》Impacted As hashtagPlanned Method
•Begin with As Planned Schedule
•Add Owner or Contractor Delays
•Compute Owner caused delay & Contractor caused delay

3》Collapsed (But for) As Built Method
•Begin with As Built Schedule, including Owner and Contractor Delays
•Remove Owner (Contractor) caused delays
•Resulting schedule shows when Contractor (Owner) would have finished “but for” Owner (Contractor) delays

Benefits:
•Very good accuracy
Shortcomings:
•No allowance for hashtagmitigation of delays

4》Contemporaneous Period (Windows) Analysis
•Begin with As Planned Schedule
•Select periods (windows) to analyze
•Enter actual progress and delay activities using contemporaneous project documents
•Calculate the schedule
•Repeat the process for the next window

Benefits:
•Most accurate results
•Considers hashtagdynamic nature of the hashtagcritical path Shortcomings
hashtagTime consuming
hashtagCostly to prepare